How Many Blocks a Block Machine Makes Per Day

Every block machine is sold on a number: blocks per shift. It is also the number most often misread, because it is a rated figure for a working shift, not a cycle time multiplied out over 24 hours. This page sets out how the number is built, what actually moves it, and the published per-shift output for every model in the range, so you can check a quotation against arithmetic rather than against a brochure.

By Alex, RENFA
Last reviewed 2026-10-29 · 5 min read

What the per-shift figure actually means

The output on a specification sheet is blocks per shift, not blocks per hour and not blocks per day. A shift is a working period: mix is supplied, blocks are demoulded and taken away, and the machine stops when one of those stops. The rated figure already assumes the machine is fed and cleared, which is why it is lower than the cycle time multiplied out over the same hours.

So the honest way to read it is as a ceiling for a well-run shift. If your mix supply is manual and your curing area is small, you will not reach it, and no machine will change that. The figure tells you what the machine can do when the work around it keeps up.

Cycle time is the multiplier

Moulding cycle is the time from one block being ejected to the next one being ejected. It fixes how many strokes the machine can make in an hour, and every other output figure follows from it.

This range runs two cycles. On a 45-second cycle the machine completes 80 strokes in an hour; on a 35-second cycle, about 103. That is roughly 29 per cent more strokes for the same hour of work, which is why a 35-second machine is not simply a heavier version of a 45-second one — it is a different production rate.

  • 45-second cycle — 80 strokes per hour
  • 35-second cycle — about 103 strokes per hour

The mould sets how many blocks come out of each stroke

Strokes per hour is only half the calculation. The other half is how many blocks the mould box produces per stroke, and that is a property of the mould, not the machine.

This is where most comparisons go wrong. The same machine, with two different moulds, gives two very different numbers. The published figures below show it plainly on one model: the standard brick profile produces several times the piece count of a 390 × 190 × 190 mm hollow block, because the block is several times the volume of concrete. A machine is not fast or slow in the abstract; it is fast or slow at a particular product.

That also means the mould list is a commercial decision before it is a technical one. If you intend to sell hollow blocks and pavers, the machine has to be specified for both, and the output figure you should be quoted is the one for the product you will actually run most.

What a charging hopper changes

A charging hopper feeds the mould box without the operator shovelling into it each cycle. On this range it shows up directly in the published output: the same 35-second machine is rated at 2,400 hollow blocks per shift without a hopper and 3,200 with one, and at 15,000 against 20,000 standard bricks.

That is a third more output from the same cycle time, and it is the single largest jump available inside one model family. It also removes the operator from the most repetitive part of the job, which matters more on a long shift than the headline percentage suggests.

Published output for every model in the range

These are the factory-rated per-shift figures for the current range. Standard brick is 240 × 53 × 115 mm; hollow block is 390 × 190 × 190 mm. Both columns are per shift, not per hour.

  • R2-45 Small Mobile — 45 s cycle, 1.1 kW — 3,600 standard bricks or 600 hollow blocks per shift
  • RD2-45 Diesel Mobile — 45 s cycle, 8 hp diesel — 3,600 standard bricks or 600 hollow blocks per shift
  • R3-45 Directly Mobile — 45 s cycle, 1.1 kW — 8,000 standard bricks or 1,000 hollow blocks per shift
  • R4-45 Large Mobile — 45 s cycle, 3.7 kW — 12,000 standard bricks or 1,800 hollow blocks per shift
  • R4-35A — 35 s cycle, 4.8 kW — 15,000 standard bricks or 2,400 hollow blocks per shift
  • R4-35AH with hopper — 35 s cycle, 4.8 kW — 20,000 standard bricks or 3,200 hollow blocks per shift
  • R4-35B — 35 s cycle, 6.3 kW — 15,000 standard bricks or 2,400 hollow blocks per shift
  • R4-35BH with hopper — 35 s cycle, 6.3 kW — 20,000 standard bricks or 3,200 hollow blocks per shift

What actually cuts a shift short

The gap between the rated figure and what a yard produces is almost never the machine. It is one of five things, and they are worth checking before you buy a bigger model to compensate.

Mix supply comes first. A machine on a 35-second cycle needs a fresh batch every 35 seconds; if the mixer, the sand or the cement delivery cannot sustain that, the cycle stretches and the extra capacity is wasted. Curing and pallet turnaround come second — blocks that cannot be moved out block the next stroke.

Power stability is the third. A machine that stops and restarts through an unstable supply loses more than the downtime, because the first blocks after a restart are often rejected. Mould wear is the fourth: a worn mould box produces blocks that need more finishing, which slows the end of the line. Labour is the fifth, and it is the one a hopper addresses most directly.

Turn it into a target before you choose a model

Work backwards. Decide how many blocks you can sell and cure in a day, then find the model whose published per-shift figure for your main product sits slightly above that number — not far above it. A machine rated at twice your curing capacity does not produce twice as much; it idles between batches.

Then check the two multipliers against your own site: can your supply keep a 35-second cycle fed, and does your power hold a 4.8 kW or 6.3 kW motor through a shift. If either answer is no, the smaller model with a reliable shift will out-produce the larger one that keeps stopping.

The number to ask for

When you request a quotation, ask for the per-shift figure for the exact product you intend to sell, not a single headline number. On this range the same machine can be rated at 2,400 or 3,200 hollow blocks depending on whether it carries a hopper, and at 15,000 or 20,000 bricks for the same reason.

Common questions

How many blocks does a block machine make in an hour?

Strokes per hour come from the moulding cycle: about 80 on a 45-second cycle and about 103 on a 35-second cycle. Blocks per hour is that figure multiplied by how many blocks the mould box produces per stroke, which depends on the mould, not the machine.

Why is the rated output lower than the cycle time multiplied out?

Because the rated figure is for a working shift, not for a machine running uninterrupted. It assumes mix is supplied and blocks are cleared as they come out. Where either of those lags, actual output falls below the rating — and that is a site problem, not a machine fault.

Does a charging hopper really increase output?

On this range it does, and the published figures show it: the same 35-second machine is rated at 2,400 hollow blocks per shift without a hopper and 3,200 with one. It also takes the operator out of the most repetitive part of the cycle.

Can the same machine produce bricks and hollow blocks?

Yes, with the right mould box for each profile. The output figure changes with the mould, because a hollow block uses several times the concrete of a standard brick. That is why the quotation should name the product it is rated for.

Talk to us about this

Send the specification you have arrived at and we will confirm which model of ours matches it, with the price and the packing weight.

More buying guides

Preparing a Site for a Block Machine

What to have ready before a block machine arrives: the surface it stands on, delivery access, the power connection, mix storage and curing space.

4 min read

How to Compare Two Block Machine Quotations

Two quotations that look different usually are not. What to put on the same basis — price terms, moulds, voltage, spares and installation — before you decide.

4 min read

How to Choose a Block Making Machine

Cycle time, drive power, mould configuration and power supply — the four decisions that set the output and cost of a block making machine before you order.

6 min read

Get a specification confirmed, not a brochure