How to Compare Two Block Machine Quotations

Two suppliers quote, the numbers differ by a third, and the cheaper one looks obvious. It usually is not. Most of the gap is not margin; it is two quotations describing different things — a different price basis, a different number of moulds, a different voltage, or installation included on one side and quietly excluded on the other. This page is the checklist that puts both offers on one basis before you compare them.

By Alex, RENFA
Last reviewed 2026-10-29 · 4 min read

Put both quotations on the same basis first

A quotation is not a price, it is a set of promises with a number attached. Before comparing two of them, make sure both are promising the same thing. Until they are, the difference between the figures tells you nothing about which supplier is cheaper.

The practical way to do it is to send both suppliers the same short list of questions and require an answer against each line. Any line left blank is a cost you will meet later, not a saving you have made.

Price basis: EXW, FOB or CIF

The same machine quoted EXW and CIF can differ by a large margin and still be the same machine at the same factory gate. EXW means the machine is yours at the works; you arrange and pay for inland transport, export clearance, ocean freight and insurance. FOB moves the handover to the port of loading. CIF carries it to your destination port, and still excludes import duty, clearing and delivery to your site.

So the first line on the comparison sheet is the Incoterm, and the second is what sits outside it. A CIF quote that excludes destination clearing is not comparable with an EXW quote plus your own freight forwarder's numbers — you have to add those to the EXW side yourself.

Moulds: how many, and which profiles

On this range one mould box is included with the machine; additional profiles are separate items. That single line explains most of the price gap between two offers that otherwise look identical.

So ask both suppliers to list the mould boxes included, by product profile, and the price of each additional one. Two profiles against one profile is a real difference in what the machine can sell on day one. Also ask how many blocks each mould produces per stroke — the cavity count — because a mould with more cavities costs more and produces more, and a quotation that hides the cavity count is hiding the comparison.

Voltage and frequency must match your supply

A machine specified for the wrong supply is not a machine that needs an adapter. Voltage and frequency are agreed at the order stage, and frequency in particular cannot be re-rated on arrival — a machine built for one frequency will not run correctly on another, whatever the voltage label says.

So both suppliers should state the exact voltage and frequency they are quoting for, and you should state what your site actually has. If one quote is silent on it, that is not a detail; it is the assumption you will be held to.

What sits outside the number

These are the lines that decide whether the cheaper quote is actually cheaper. Ask each supplier to state, in writing, whether each item is included or excluded.

  • Inland transport from the works to the port, and export clearance
  • Ocean freight and marine insurance
  • Import duty, clearing and delivery to your site
  • Foundation or hardstanding preparation
  • Installation and commissioning on site
  • Operator training
  • The first spares kit and any consumables
  • Packing for sea freight, and whether crating is charged separately

The first spares list

Every machine has wear items, and the question is not whether they wear but whether you can get replacements without stopping for a month. Ask both suppliers for the list of parts they expect to be replaced in the first year, and which of those are in the quotation.

A quote that includes a spares kit and one that does not are not the same price, even when the headline figure matches. The same applies to whether the supplier can name the part rather than describe it — a part number and a photograph are what make a reorder possible without sending the broken piece back.

What the paperwork should name

A quotation is the only document you will have when something is disputed six months later. It should name the model and the mould profiles, the voltage and frequency, the price basis, what is included and excluded, and the delivery terms in a form you can hold someone to.

If a supplier will not put a term in writing, treat it as not offered. That applies equally to both sides of the comparison.

The comparison sheet

Send this to both suppliers and fill it in side by side. Where a line is blank on one side, that is the number you are missing, not a saving.

  • Model and the mould profiles included
  • Price basis: EXW, FOB or CIF — and what it excludes
  • Voltage and frequency quoted
  • Cavity count for each mould
  • Price of each additional mould profile
  • Installation, commissioning and training: included or not
  • First-year spares list, and which parts are included
  • Packing and crating: included or charged separately
  • Warranty terms, in writing
The one question that settles most of it

Ask both suppliers: “On this price, what do I still have to pay before the first block comes out?” The answers are usually different, and the difference is the real comparison.

Common questions

Why are two quotations for the same machine so different in price?

Usually because they are not quoting the same thing. The common causes are a different price basis, a different number of mould profiles, a different voltage specification, or installation and a spares kit included on one side and excluded on the other.

Is EXW or CIF better?

Neither is better in itself; they place the freight risk in different hands. CIF is simpler if you do not have a freight forwarder, but it still excludes duty, clearing and delivery to your site. EXW plus your own forwarder is often cheaper, but you carry the shipping work.

How many moulds should a quotation include?

One mould box is included with the machine on this range, and additional product profiles are separate items. How many you need is decided by what you intend to sell, not by the machine.

Does voltage matter if I can fit a transformer?

A transformer addresses voltage, not frequency. Frequency is fixed when the machine is built and cannot be corrected on site, so it has to be agreed at the order stage.

Talk to us about this

Send the specification you have arrived at and we will confirm which model of ours matches it, with the price and the packing weight.

More buying guides

Preparing a Site for a Block Machine

What to have ready before a block machine arrives: the surface it stands on, delivery access, the power connection, mix storage and curing space.

4 min read

How to Choose a Block Making Machine

Cycle time, drive power, mould configuration and power supply — the four decisions that set the output and cost of a block making machine before you order.

6 min read

Get a specification confirmed, not a brochure

Send the requirement you have worked out — capacity, power supply, bar size or slab area — and we will confirm the model, the price and the packed weight.